| Daily Construction Report | |||||
| Project: Sigma Phi Epsilon House | Date: 11/07/11 | ||||
| Contractor:Lionberger Construction Company | |||||
| Client: Virginia Tech | |||||
| Project Scope/Method of construction: The Sigma Phi Epsilon House will house 40+ brothers and be a place for brothers to study, work, and grow together. It is a three story, 22,000 sq. ft. southern fraternity style, house complete with a study lounge, game room, kitchen, full basement, and even a classroom, along with all of the bedrooms. Most bedrooms will house two brothers and each room will share a bathroom with the room beside it. The project will be done by summer of 2012. | |||||
| Sunny | Clear | Overcast | Rain | Snow | |
| Weather | |||||
| Below 32 | 33-50 | 51-70 | 71-90 | Above 91 | |
| Temp. | |||||
| Still | Moderate | High | |||
| Wind | |||||
| Dry | Moderate | Humid | |||
| Humidity | |||||
| Non Manual | Manual | ||||
| Field Force: | 1 | 6 | |||
| Subcontractors: | "Graders" | ||||
| Blacksburg Fencing | |||||
| "Sign-Installers" | |||||
| Balzer and Associates | |||||
| Schnabel | |||||
| Equiptment at | |||||
| Site: | Bulldozer(1) | ||||
| Skid-Steer (1) | |||||
| Backhoe (1) | |||||
| Is equiptment close? Yes, there is not a lot of equiptment on this site because it is just a large scale residential home. The jobsite is also surrounded by a road and a working golf course so there is not a lot of room to expand. | |||||
| Are there idle workers? No | |||||
| Construction Activities: There are three guys hauling dirt off the job site, one driving a dump truck, one using a bulldozer and the other using a backhoe. Two men are setting up the safety fence while another goes behind putting up safety signs and signs the depict what is being built on the job site. Stone is being added to the building pad and then being leveled to the final sub grade. | |||||
| Does safety seem to be of importance? The safety fence and signs were being installed as we walked up and all workers on site were wearing their PPE. | |||||
| Comments/Remarks: According to the on site Assistant Super-Intendent someone from Schnabel Engineering had dropped by earlier in the day and said that the site had sufficient soil stablization so they were preparing the final sub-grade and the final project for the day was to stake out the building corners. | |||||
Final sub-grade for "The" Sigma Phi Epsilon fraternity house
Safety fence and sign around the building site
Safety fence, main project trailer, and crest of "The" Sigma Phi Epsilon