| Project: Sigma Phi Epsilon House | Date: 11/18/11 | ||||
| Contractor:Lionberger Construction Company | |||||
| Client: Virginia Tech | |||||
| Project Scope/Method of construction: The Sigma Phi Epsilon House will house 40+ brothers and be a place for brothers to study, work, and grow together. It is a three story, 22,000 sq. ft. southern fraternity style, house complete with a study lounge, game room, kitchen, full basement, and even a classroom, along with all of the bedrooms. Most bedrooms will house two brothers and each room will share a bathroom with the room beside it. The project will be done by summer of 2012. | |||||
| Sunny | Clear | Overcast | Rain | Snow | |
| Weather | |||||
| Below 32 | 33-50 | 51-70 | 71-90 | Above 91 | |
| Temp. | |||||
| Still | Moderate | High | |||
| Wind | |||||
| Dry | Moderate | Humid | |||
| Humidity | |||||
| Non Manual | Manual | ||||
| Field Force: | 1 | 9+ | |||
| Subcontractors: | Schnabel | ||||
| Procon | |||||
| Equiptment at | |||||
| Site: | Mini Excavator (1) | ||||
| Skid- Steer (1) | |||||
| Construction Activities: Procon was finishing digging the footings. Someone from Schnabel was checking for soft spots. So far three were found. | |||||
| Does safety seem to be of importance? Everyone is wearing the proper PPE and the assistant super-intendent informed me that earlier today he had gone through and checked the entire site for any new hazzards or safety issues that weren't there earlier in the week. | |||||
| Comments/Remarks: Because of rain, water had to be pumped off the foundation for the previous two days and the project had to be delayed. The three soft spots that the Schabel engineer found were fixed by digging down deeper than normally neccesary and replacing that dirt with "flowable fill". | |||||
Tying in re-bar