Daily Construction Report
Project: Signature Engineering Building Date: 9/28/11
Contractor: Gilbane
Client: Virginia Tech
Project Scope/Method of construction: This building "will be approximately a 160,000 gross-square-foot facility to include classrooms, instructional laboratories, research laboratories, and offices for multiple departments and programs for the College of Engineering."
Sunny Clear Overcast Rain Snow
Weather
Below 32 33-50 51-70 71-90 Above 91
Temp.
Still Moderate High
Wind
Dry Moderate Humid
Humidity
Non Manual Manual
Field Force: 1 11+
Equiptment at
Site: Bulldozers(3)
Dump-Trucks(3)
Excavator (1)
Backhoe (1)
Is equiptment close? Yes. For such a big project, I would say everything is pretty close.
Are there idle workers? None that I can see. All the machines have an opperator, and it seems as though everyone knows their job and is doing it.
Construction Activities: Excavation of the parking lot. They are ripping up the old asphalt and loading it into dump-trucks to be hauled off.
Does safety seem to be of importance? Yes, all workers are wearing safety gear and all machine operators are acting responsibly.

Hazard Analysis:

Activity Hazard Solution
Excavation There are a lot of big, powerful  Everyone do their job and act
machines moving very heavy loads responsibly
Comments/Remarks: This is the beginning of a very large project and it is the first comercial project that I have payed attention to from the beginning of the project. It will be interesting to see it go through different stages.